Emergency prevention
On the refinery territory there are three protective structures (shelters):
Shelter #43 is built into Administration building #2, has 3 classes, capacity up to 450 people, has the status “partially ready”
Shelter #44 is built into the administrative building of NRM LLP, has 3 classes, capacity up to 450 people, status “partially ready”
Shelter #45 is built into the administrative building of YuzhATS LLP, has 3 classes, capacity up to 400 people, has status “ready”
All employees working on the refinery territory have individual personal protective equipment according to their activities:
All employees working on the refinery territory have individual personal protective equipment according to their activities:
In order to prevent and eliminate fires, all units and sections are equipped with automatic fire-fighting systems; administration and amenity buildings, control rooms with automatic and manual fire detectors, fire panels, fire extinguishers. The company has a fire-fighting pipeline with a total length of 24,980 m. In order to respond quickly to the consequences of an accident at the refinery, an instruction has been developed defining the officials involved in the elimination of the consequences of accidents at the refinery.
The following Preventive Activities are held on annual basis:
- In case of natural and man-made emergencies, the refinery budget provides for financing of emergency recovery works and purchase of necessary materials
- Every year on the refinery territory, works are planned to carry out and perform urgent works on preparation for the winter and summer period, planned and preventive repair of the equipment is drawn up, measures are carried out to ensure primary fire safety measures aimed at reducing fires on the territory of the facility
- There is also regular inspection of outdoor fire-fighting water sources with representatives of Fire Department “Ort Sondirushi”
- Before the start of the fire-hazardous period, an order is issued on the maintenance of the process mode, during the loading and unloading works on the railway trestles of the goods and transport control
- In order to eliminate vegetation, the refinery territory is mowed and treated with chemical solution
- Prior to the beginning of the flood period, measures are being taken to prevent and eliminate the consequences of floods
- The employees of the enterprise are constantly informed about compliance with fire safety rules, the procedure for carrying out fire and gas-hazardous works, as well as about liability for violation of safety rules and measures